Registering Property in India, Hyderabad
BUILDING A WAREHOUSEData as of: January 2006
City: Hyderabad
Registration Requirements:
| Procedure 1 | Obtain land use permission from Hyderabad Urban development authority |
| Time to complete: | 3 days |
| Cost to complete: | INR 12,050 (INR 10,000-14,100) |
| Comment: | |
| Procedure 2 | Apply for building permit and No Objection Certificate and pay initial fee |
| Time to complete: | 5 days |
| Cost to complete: | INR 11500 |
| Comment: | The company must submit the application in Form A to the Hyderabad Urban Development Authority along with the following documents: a) Building application duly signed by the owner; b) Builder and architect, engineer; c) Declaration forms duly signed by th |
| Procedure 3 | Obtain approval of plans (building permit) and pay final fees |
| Time to complete: | 30 days |
| Cost to complete: | INR 30000 |
| Comment: | Application will be scrutinized. If the application is fit to be approved, a demand will be sent to you by the local authority for payment of license fee and development charges if any. The rate will depend on the proposed uses and the floor area. Once th |
| Procedure 4 | Notify the Municipal Corporation about commencement of earth work for foundation |
| Time to complete: | 45 days |
| Cost to complete: | INR 5,000 (fee for all inspections) |
| Comment: | |
| Procedure 5* | Receive foundation inspection and commencement certificate |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 6* | Notify the Municipal Corporation before the start of foundation concreting |
| Time to complete: | 43 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 7* | Receive foundation concreting inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 8* | Notify the Municipal Corporation before the start of laying the roof and basement floor work |
| Time to complete: | 41 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 9* | Receive roof inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 10* | Notify the Municipal Corporation about of completion finishing work |
| Time to complete: | 39 days |
| Cost to complete: | no charge |
| Comment: | The company should inform the local authority about completion of the finishing work (white waxing, coloring, fixing, water supply, drainage, or other sanitary fitments), before obtaining regular connection for water supply/electricity. |
| Procedure 11* | Receive finishing work inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 12 | Obtain no objection certificate from fire department |
| Time to complete: | 30 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Procedure 13* | Receive inspection from fire department |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 14* | Apply for the use and uplift of underground water with the Andhra Pradesh pollution control board |
| Time to complete: | 15 days |
| Cost to complete: | INR 5000 |
| Comment: | |
| Procedure 15* | Receive inspection from Andhra Pradesh pollution control board |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 16* | Obtain no objections certificate from Public Health Department |
| Time to complete: | 10 days |
| Cost to complete: | INR 3500 |
| Comment: | |
| Procedure 17* | Apply for sanction of power connection with A.P. Central Power Distribution Company |
| Time to complete: | 45 days |
| Cost to complete: | INR 75,000 (INR 50,000-100,000) |
| Comment: | |
| Procedure 18* | Receive inspection from A.P. Central Power Distribution Company |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 19* | Obtain water and sewage connection from Hyderabad Metropolitan Water Supply and Sewerage Board |
| Time to complete: | 15 days |
| Cost to complete: | INR 7500 |
| Comment: | |
| Procedure 20* | Obtain phone connection |
| Time to complete: | 7 days |
| Cost to complete: | INR 2000 |
| Comment: | |
| Procedure 21 | Obtain completion certificate |
| Time to complete: | 20 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Procedure 22* | Receive final inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 23 | Obtain occupancy permit |
| Time to complete: | 15 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Procedure 24* | Receive inspection for obtaining occupancy permit |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: |